Skip to content

Concrete Work for DIY Builders

Bags or ready-mix · Reinforcement and release oil · Joints and surface treatment · Step by step

Concrete is the most widely used building material in the world — and one of the most common tasks for DIY builders. Whether you are pouring a garage floor, a foundation for a garden building, stair footings or a column, the principles are the same: correct volume, correct strength class, correct reinforcement and correct curing. This guide covers the entire process from planning to finished surface.

Permit requirements: Foundations and other concrete works that form part of load-bearing structures may require permits or involvement of responsible professionals, depending on the project. Check with your local authority before starting work.

Layer build-up — from bottom to top

A correctly constructed ground-bearing concrete slab consists of several layers. Each layer serves a purpose — skip one and the result is compromised.

Gravel / aggregate (capillary break)PE filmReinforcement mesh25 mmThickness↑ Expansion strip along edges
Cross-section of a reinforced concrete slab with all layers
  1. Subgrade / compacted fill — load-bearing ground with a frost-safe solution for the actual site
  2. Gravel / aggregate, 150200 mm — capillary break layer, prevents moisture wicking
  3. PE membrane / construction membrane to suit the system — vapour or moisture barrier against the ground, with overlaps and taping in accordance with the manufacturer's instructions
  4. Expansion strip along edges — isolates slab from foundation wall, absorbs movement
  5. Reinforcement mesh on spacers — position and cover must follow the design or documented system solution
  6. Concrete with selected strength class and thickness — strength class, exposure class and slab thickness must be chosen from load, environment and the designed solution
  7. Levelled surface / self-levelling compound if required — ready for floor covering

Bags vs. ready-mix concrete

  • Under 0.30 — bagged concrete (25 kg = approx. 0.0125 ) is simplest and cheapest
  • 0.301.0 — consider bulk bag concrete (IBC) or bagged depending on access
  • Over 1.0 — ready-mix truck delivery (minimum order typically approx. 3 )
💡 Include a sensible ordering margin. The amount of extra material needed depends on geometry, formwork, waste and the delivery method.

Concrete strength classes

Concrete is classified by its characteristic compressive strength after 28 days of curing (C[cylinder]/[cube] MPa). For DIY work, C20/25 and C25/30 are the most common classes.

ClassStrength (28 d)Typical application
C16/2016 MPa (cyl.) / 20 MPa (cube)Example of a lower strength class — suitability depends on exposure and design
C20/2520 MPa (cyl.) / 25 MPa (cube)Common class in simpler building work — final selection depends on exposure and design
C25/3025 MPa (cyl.) / 30 MPa (cube)Common class for many structural uses — still subject to load and exposure requirements
C30/3730 MPa (cyl.) / 37 MPa (cube)Higher strength class used where loading and exposure demand it
Common concrete strength classes — final class must be selected from structural and exposure requirements

Reinforcement

Plain concrete is strong in compression but weak in tension. Reinforcement is used where the design requires it to carry tension, limit cracking and provide the required robustness and capacity. For load-bearing structures, reinforcement and detailing must always be designed or otherwise documented.

Reinforcement mesh — for slabs

Reinforcement mesh consists of welded steel mats supplied in standard sheets (typically 2.35 × 5.85 m = 13.7 ) or rolls. They are faster to lay than individual bars and provide uniform reinforcement distribution.

TypeMesh spacingBar dia.Application
K131150×150 mmø5 mmLight slabs, indoor floors
K188150×150 mmø6 mmExterior slabs, garages, decks
K257150×150 mmø7 mmHeavy slabs, storage buildings
B500100×100 mmø5 mmClose mesh, special requirements
Common reinforcement mesh — supplied in sheets 2.35×5.85 m (approx. 13.7 m²/sheet) or rolls
  • Place mesh on plastic spacers (2530 mm) — ensures correct cover
  • Overlap between sheets: min. 2 mesh spacings = approx. 300 mm
  • Tie overlaps with binding wire
  • Calculate net area + 15–20% for overlaps when ordering

Rebar — for foundations and columns

Strip foundations and columns use longitudinal bars and stirrups. Longitudinal bars carry load; stirrups hold them in position and prevent buckling.

DiameterCross-sectionWeightCommon use
ø8 mm50 mm²0.39 kg/lmStirrups, assembly bars, light slabs
ø10 mm79 mm²0.62 kg/lmSlabs, light footings
ø12 mm113 mm²0.89 kg/lmBeams, foundations, columns
ø16 mm201 mm²1.58 kg/lmHeavy beams and columns
Rebar B500NC — common Norwegian/European examples; final reinforcement must be project-specific
  • Strip foundations and columns must be reinforced in accordance with the project design. Bar count, diameters and stirrup spacing cannot be fixed generically in a simplified guide
  • Stirrup dimensions and cutting lengths must be calculated from the actual geometry, bend radius, cover and reinforcement system
  • Cover: 25 mm against internal formwork, 50 mm against soil
  • Lap splice length: min. 40 × bar diameter (e.g. ø12480 mm)
⚠️ Reinforcement in load-bearing structures must be designed by a qualified structural engineer. The tables and tips here are indicative only and must not be used as a substitute for structural design.

Formwork and release oil

Formwork holds the concrete in place while it cures. Adequate application of release oil is essential so the formwork can be stripped without damaging the concrete surface.

Formwork materials

  • Formwork board 22×100 mm — economical, can be reused 3–5 times
  • OSB sheet 18 mm — for larger flat formwork and walls, smoother surface finish
  • Column formers / shuttering tubes — for columns and some prefabricated edge solutions
  • Stakes and wedges — keep formwork straight and stable against concrete pressure; bracing requirements depend on height, geometry and pour rate

Release oil

  • Approved release oil (vegetable or mineral-based) — apply by brush or spray
  • Typical consumption: 0.100.20 L/ of formwork area
  • Use only approved release agents. Used engine oil and other unsuitable oils should not be used
  • Allow 15–30 minutes for the oil to be absorbed before pouring
💡 Porous formwork materials may require more release agent than dense surfaces. Always follow the product data sheet for application method and coverage.

PE membrane and capillary break layer

Under all ground-bearing concrete slabs, a capillary break layer and a moisture barrier must be installed. Without these, ground moisture will wick up into the slab and damage floor coverings and indoor air quality.

  • Gravel/aggregate 8–32 mm, min. 150 mm thick — breaks capillary rise from the ground
  • Construction membrane to suit the system — installed as the moisture / vapour barrier in accordance with the project or documented system
  • Overlap at joints: min. 200 mm, tape all joints
  • Turn membrane up at edges and clamp in place with the expansion strip
  • Calculate area + 10% for overlaps when ordering

Expansion joints and edge strip

Concrete moves due to temperature, shrinkage and restraint. The joint layout should limit uncontrolled cracking and must be adapted to slab thickness, geometry, reinforcement and drying conditions.

Expansion strip along edges

  • Installed around the full perimeter against the foundation wall — 10 mm thickness is standard
  • Also acts as thermal insulation and prevents cold bridging
  • Available in EPS (white) or mineral wool — EPS is most common for outdoor use
  • Calculate: perimeter of slab = 2 × (L + W) lm

Construction joints in large slabs

  • The need for control joints must be assessed from slab thickness, geometry, restraint and reinforcement. A common rule of thumb is joint spacing of about 24–36 times the slab thickness, but the designed solution takes precedence
  • Saw-cut control joints when the concrete is ready for cutting without raveling, and with depth and timing suited to the chosen method and documented practice
  • Any sealing or joint filling must be selected for the movement, exposure and intended use, in accordance with the sealant manufacturer's instructions

Admixtures

Admixtures are mixed into the concrete to modify its properties. For bagged concrete, follow the manufacturer's mixing instructions; admixtures are most relevant for ready-mix orders.

AdmixtureEffectWhen to use
Plasticiser (water reducer)Increases workability without extra waterCongested formwork, pump concrete
Air-entraining agent (AEA)Frost resistanceExposed outdoor use, salt exposure
AcceleratorFaster strength gainPouring below +5 °C, shorter strip time
RetarderExtended open timeLong hauls, hot summer conditions
Polypropylene fibres (PP)Reduces plastic shrinkage crackingThin slabs, crack-prone surfaces

Surface treatment and curing

Fresh concrete is porous and grey. Surface treatment protects against moisture, frost and chemicals, and improves appearance.

Curing compound

  • Sprayed onto fresh concrete immediately after finishing
  • Prevents premature evaporation of water — critical in hot and/or windy weather
  • Consumption: approx. 0.150.20 L/
  • Alternative: cover with plastic sheeting for 7 days

Concrete sealing and coating (after curing)

  • Impregnation — a breathable water-repellent treatment may be suitable outdoors. Select the product for the exposure class and follow the data sheet for coverage and application
  • Epoxy coating — dense and wear-resistant for some interior floors, but only where residual moisture, substrate preparation and primer all meet the system requirements. Follow the supplier's data sheets
  • Concrete paint / floor paint — lighter treatment where the selected system is suitable for the substrate and the intended use
💡 Wait until the concrete meets the coating manufacturer's requirements for curing time and residual moisture before applying dense coatings. Applying too early can cause blistering, poor adhesion and failure.

Step-by-step guide

Step 1 — Planning and excavation

  • Mark out corners with a string line — check diagonals for square (equal diagonals = right angle)
  • Excavate to the designed depth and frost-safe solution for the site + slab thickness + gravel layer
  • Lay drainage pipe at the base if groundwater is a concern, then compact gravel in layers

Step 2 — PE membrane and expansion strip

  • Lay PE membrane with 200 mm overlap and tape all joints
  • Turn membrane up at edges — tape to existing wall or foundation
  • Install expansion strip (10 mm EPS) around the full perimeter

Step 3 — Formwork

  • Fix formwork boards along the outer edges to the correct level — this defines the finished slab height
  • Brace the formwork sufficiently for its height, geometry and the expected concrete pressure
  • Apply 2 coats of release oil to the inside face — allow 15–30 min to absorb

Step 4 — Reinforcement

  • Place suitable spacers so the reinforcement stays at the designed level and maintains the required cover throughout the pour
  • Lay reinforcement mesh with 300 mm laps — tie with binding wire
  • The reinforcement mesh must be placed at the designed level. For crack-control reinforcement in slabs-on-ground it is often placed in the upper half / upper third, but the final position depends on the structural solution
  • For double reinforcement, both the upper and lower layers must have the specified cover and the correct spacing between layers

Step 5 — Mixing and pouring

  • Mix bags per instructions — typically 3.0–3.5 L of water per 25 kg. Never add more water than specified
  • Pour from the lowest point and work upwards — do not drag concrete sideways with a shovel. Place a slab in one full-depth operation; deep pours such as walls and columns are placed and compacted in layers (lifts) so each layer is properly compacted before the next
  • Compact the concrete with suitable equipment and method without over-vibration. Execution depends on consistency, thickness, reinforcement density and the selected concrete mix
  • Strike off the surface continuously with a screed board

Step 6 — Screeding and finishing

  • Draw a screed board across the top of the formwork for final levelling
  • Steel-float the surface after approx. 1–2 hours (once bleed water has been absorbed)
  • For outdoor use: broom-finish for a slip-resistant surface
  • Spray on curing compound immediately after floating

Step 7 — Curing and stripping

  • Cover with plastic sheeting immediately — alternative to curing compound
  • Wet the surface 1–2 times per day for the first 3–7 days in hot weather
  • Cold weather: do not pour onto frozen ground, and do not let fresh concrete freeze before it has gained enough strength — use cold-weather measures (protection, insulated covers, a suitable mix) and follow the supplier's minimum-temperature guidance. Hot, dry or windy weather needs the opposite care so it does not dry out too fast
  • Strip formwork only when the concrete has reached sufficient strength for the geometry, temperature conditions and expected loading
  • Loading and follow-on work must be adapted to the concrete's achieved strength, temperature conditions and the designed solution
  • Carry out any control joints when the concrete is ready for saw cutting in accordance with the chosen method and documented practice

Rules of thumb and reference figures

ParameterValue
25 kg bagapprox. 0.0125 m³ (12.5 L)
Concrete densityapprox. 2,400 kg/m³
Ground-bearing slab thicknessMust be selected from loading, soil conditions, reinforcement and the designed solution
Cover depthMust follow exposure class, environment and the designed solution
Frost protectionMust be determined for the actual site using local climate data and the chosen structural solution
Control jointsA common rule of thumb is about 24–36 × slab thickness, but the designed solution takes precedence
Ready-mix concrete, minimum orderVaries by supplier, plant location and delivery method
Mesh lapmin. 2 mesh spacings (approx. 300 mm)
Bar splice (lap length)min. 40 × bar diameter
Release oil consumption0.10–0.20 L/m² of formwork area
PE membrane / construction membrane, lapmin. 200 mm per system
Expansion strip thickness10 mm (EPS or mineral wool)
Curing and strip timeMust be assessed from temperature, geometry, cement type, mix design and achieved strength
28-day design strengthReference point for structural design; concrete continues gaining strength beyond 28 days
Concrete densityapprox. 2,400 kg/m³
25 kg bagapprox. 0.0125 m³ (12.5 L)

Common mistakes

  • Adding too much water — makes mixing easier, but reduces strength; always follow the water ratio on the bag
  • Pouring in freezing conditions without protection — concrete below +5 °C will not cure and can be destroyed by frost
  • No vibration around tight reinforcement — voids and pores weaken the structure and create pathways for water
  • Pouring layers that are too thick — pour a maximum of 300 mm at a time and vibrate each layer separately
  • Insufficient cover over reinforcement — minimum 25 mm indoors, 40–50 mm against soil or moisture
  • Stopping curing too early — concrete needs to be kept moist for at least 7 days to achieve full strength
  • Pouring against dry formwork — without wetting or release agent the formwork draws water from the concrete, leaving a weak surface

Calculate your materials

Use the calculator to find the number of bags, reinforcement, membrane and extras:

Tools you'll need

The kit this job actually calls for, and whether it's worth buying or renting for one weekend.

  • Cement mixer

    Above roughly half a cubic metre, hand mixing stops being realistic.

    Buy 150–400 €
    Rent 25–50 €/day
    rent this one
  • Wheelbarrow

    A builder's barrow with a pneumatic tyre, not a garden one.

    Buy 50–120 €
  • Shovel and spade

    A square shovel for mixing and moving, a spade for digging.

    Buy 15–40 €
  • Screed board / straightedge

    Screeding off the forms is what makes a slab flat.

    Buy 20–60 €
  • Float

    Wood or magnesium float brings the fines up after screeding.

    Buy 10–25 €
  • Steel finishing trowel

    Only once the bleed water has gone, or you seal it in.

    Buy 15–40 €
  • Spirit level

    Get a 1.2 m one — short levels lie on long runs.

    Buy 15–60 €
  • Mixing buckets

    Two at least, 10 L+, so you can mix and rinse.

    Buy 5–15 €
  • Safety glasses, gloves and dust mask

    Wet concrete burns skin — gloves and long sleeves, not just glasses.

    Buy 15–40 €

Prices are indicative for DIY-grade tools and vary a lot by brand and region — treat them as a budgeting starting point, not a quote. Rental rates are per day from a typical tool rental shop.

Frequently asked questions

What concrete strength (PSI) should I use for footings?

3000 PSI is the minimum for residential footings. 4000 PSI is recommended for driveways and areas exposed to freeze-thaw cycles or deicers.

How many 80 lb bags of concrete make a cubic yard?

One 80 lb bag yields about 0.60 cubic feet. You need approximately 45 bags to make 1 cubic yard (27 cubic feet).

How long does concrete take to cure?

As a rough guide concrete is walkable in about 24–48 hours, and its specified (characteristic) strength is referenced at 28 days — it keeps gaining strength slowly after that, so "28-day strength" is a reference age, not the point at which it is suddenly "fully" done. Actual times depend on the mix and temperature; avoid heavy loads early (often at least 7 days), and keep the concrete protected and moist while it cures.

This guide is intended as practical guidance for simple concrete work. Load-bearing structures, reinforcement design, strength class selection, joint layouts and frost protection must be designed or verified by a qualified professional. For admixtures, self-levelling compounds and repair mortars, always follow the specific product data sheet — coverage and mixing ratios vary between manufacturers. Last reviewed: May 2026

Free to try — no sign-up

Turn this guide into a plan

Get exact quantities and costs for your own measurements, build an itemized shopping list so you don’t overbuy, and use the PDF to collect quotes from contractors.