How to build a deck

Three variants · Ground-level, elevated and on a slope · Span tables and quantity take-off · Step by step

This guide covers the three most common deck configurations: a ground-level deck, an elevated deck and a deck built on a sloping site. You will find material lists, span tables, step-by-step instructions and a worked example with a full quantity take-off for a 6.0 × 4.0 m deck.

Planning permission: Whether a deck needs planning permission depends on your local rules, and the thresholds vary by country, state and municipality. Many jurisdictions exempt a low, unroofed deck below a certain height, projection and distance from the boundary — but the exact limits, and whether any exemption applies at all, differ widely. Figures sometimes quoted (e.g. ≤1.0 m above ground, ≤4.0 m projection, ≥1.0 m from the boundary) are only an illustrative example of one such rule set, not a universal standard. Always confirm the requirements with your local building/planning authority before you build.

Choose the right variant

VariantBest suited whenDifficulty
A — Ground-level deckFlat site, low deck, no railing neededEasy ★☆☆
B — Elevated deckLevel with door threshold, 0.5–2+ m above groundModerate ★★☆
C — Deck on a slopeSloping site, avoiding fill materialDemanding ★★★
💡 Choose a ground-level deck if the site allows — it is the cheapest, simplest to build and carries the lowest risk. If you are unsure about the wall construction, choose a freestanding elevated deck over a wall-mounted one.

Materials

Timber

Fixings and hardware

Foundations

Key principles

1 — Correct joist spacing

The spacing between deck joists depends on the board thickness:

2 — Board gap

Leave a drainage gap between boards and follow the board manufacturer's figure. As a guide, dry (kiln-dried) boards are usually laid at about 56 mm because they expand when wet; boards delivered very wet are laid tighter (about 23 mm) because they shrink as they dry to roughly the same final gap. Never close the gap completely — water and debris must be able to clear.

3 — Guard rail

Most codes require a guard rail once the fall past the deck edge exceeds a set threshold, with a minimum guard height and a maximum gap between balusters — but these values are jurisdiction-specific and differ between, for example, US (IRC) and European/Nordic codes. As an illustrative example only, some codes use roughly a 0.5 m fall trigger, a 1.0 m minimum height and a 100 mm maximum opening — but use the figures from your own local building code. Deck-edge guards, stair guards and handrails are governed by separate rules; check each.

4 — Drainage and ventilation

Good airflow beneath the structure is critical for durability. Joists should be kept as far above ground as practical, and water must be able to drain freely under the deck.

5 — Fixing to the house

The ledger beam must be fixed into the load-bearing structure of the house — never into cladding alone — and the connection must be designed for the loads (follow the connector manufacturer's guidance or have a structural engineer specify it). Just as important is keeping water out: flash over the ledger with a drip detail, hold it off the wall on spacers/standoffs so water can drain behind it, and use fasteners and brackets with a corrosion class suited to treated timber and your environment (e.g. A4 stainless near the coast). If in doubt about the wall construction, build a freestanding deck with its own posts close to the wall.

Variant A — Ground-level deck

Decking boards 28×120 mmJoists 48×98 mmPaving slabs / blocksWeed membraneGravel/aggregate 100200 mmGravel (drainage layer)Compacted ground / firm base5 mm
Cross-section — ground-level deck

Construction sequence

  1. Mark out the area with pegs and string line. Check diagonals are equal (for a true rectangle).
  2. Excavate turf, roots and soft topsoil down to firm ground.
  3. Lay weed-suppressing membrane to prevent soil mixing with the gravel over time.
  4. Fill and compact gravel or aggregate — approximately 100200 mm. A stable, free-draining layer is more important than exact depth.
  5. Place paving slabs or concrete pads as bearing points. Use a laser level to ensure all bearing points are in the same plane.
  6. Install the joist frame at 600 mm centres (for 28 mm boards). Check for level and straightness.
  7. Fix decking boards with a 5 mm gap. Two screws per board at each joist. Splices must always land on a joist.
  8. Trim edges cleanly and fit fascia boards for a neat finish.
💡 Joists running close to ground level should be supported (paving slab or block) at no more than 0.81.0 m intervals along each joist to prevent sagging and movement over time.

Variant B — Elevated deck

GroundConc.Conc.Conc.Doublebearer48×148 mm joistsDecking boards 28×120 mmRailing1.0 mHeightc/c ~2.0 m (posts)
Elevated deck — side elevation

Construction sequence

  1. Establish the finished deck height from the door threshold. A maximum step-down of 25 mm is recommended for accessible designs; otherwise aim for at least 50 mm clearance above any potential moisture source.
  2. Choose freestanding or ledger-mounted. Freestanding is simpler and safer if you are unsure of the wall construction.
  3. Mark out the bearer lines and post positions. Check right angles by measuring diagonals.
  4. Excavate and cast foundations. Ensure free-draining material in the base. Confirm the local frost depth and build foundations below it.
  5. Set post bases to the exact height and position while the concrete is still workable.
  6. Erect the 98×98 posts in the bases. Do not cut to final height yet.
  7. Fix the double bearer beams to the posts. Check laser level carefully in both directions.
  8. Hang deck joists (600 mm centres) with joist hangers or bearing on top of the beams. Cut posts to the correct height.
  9. Install diagonal bracing between posts and bearer beams — especially at the corners.
  10. Lay decking boards and fix with screws. Pre-drill at all ends and splices.
  11. Erect railing where the fall height exceeds 0.5 m.
Ledger fixing to the house: For a ledger-supported deck, fixings must be designed and installed in accordance with the manufacturer's guidance or by a structural engineer — the number and diameter of screws or bolts depend on the loads and the construction of the house. Fixings must always go into the load-bearing structure, never into cladding alone. Inadequate ledger fixings are one of the most common and serious faults in deck construction.

Variant C — Deck on a slope

SlopeDecking boards (level deck)Short postTall postDiagonal bracing between posts and bearer (critical!)
Deck on a slope — posts at varying heights, level deck surface

Built in the same way as an elevated deck (Variant B), but requiring greater precision in levelling and more robust bracing.

  1. Measure the ground height at all post positions with a laser. Record a height schedule.
  2. Choose your strategy: Moderate slope → single deck level with posts of varying height. Steep slope → two deck levels (stiffer structure, better appearance).
  3. Cast foundations so that all tops land in exactly the right place. Use a laser — not eye measurement.
  4. Erect posts and bearer beams — start from the highest side. Set the beams to an exact level.
  5. Cut each post individually to its correct length — do not cut all posts the same.
  6. Install deck joists in the same way as Variant B.
  7. Install generous diagonal bracing in both directions. A sloped site generates greater lateral forces — never scrimp on bracing.
  8. Lay boards and install railing wherever the fall height exceeds 0.5 m.
💡 Over-engineer rather than cut corners on a sloped site. Heavier joists and more bracing than strictly necessary is a sound investment.

Span tables (C24 treated timber)

Deck joists — indicative maximum spans

Section600 mm centres400 mm centres
48×98 mm1.6 m1.8 m
48×123 mm2.0 m2.3 m
48×148 mm2.3 m2.7 m
48×173 mm2.7 m3.2 m
48×198 mm3.1 m3.6 m
48×223 mm3.5 m4.1 m

Bearer beams — indicative maximum post spacing

SectionMax post spacing
48×198 mm (single)2.5 m
48×223 mm (single)2.9 m
2× 48×198 mm (double)3.6 m
2× 48×223 mm (double)4.1 m

Source: Bergene Holm. Applies to C24 pressure-treated structural timber. Joists hung in joist hangers (rather than bearing on top) should be reduced by a factor of 0.9.

Quantity take-off

Decking boards

Effective module width = board width + gap (e.g. 120 + 5 = 125 mm = 0.125 m)

Number of boards = deck depth / module width

Add 5–10% for cutting waste and grading.

Deck joists

Number of joist lines = ceil(dimension perpendicular to joists / spacing) + 1

Decking screws

Screws = number of boards × number of joist lines × 2

Add 10% reserve.

Concrete for point foundations

For a cylindrical foundation:

Volume () = π × radius² × depth

Example (volume only): Ø300 mm (r=0.15 m), depth=0.70 m → π × 0.15² × 0.700.049 = 49 L per foundation. The 0.70 m depth here is only an arbitrary figure for the volume sum — it is not a recommended footing depth. Required depth depends on your local frost depth (or a frost-protected design) and the ground; confirm it locally before casting.

Worked example: 6.0 × 4.0 m deck

Decking boards 28×120 mm, 5 mm gap. Boards run lengthways (6.0 m); joists run the 4.0 m way and are distributed along the 6.0 m length.

The 4.0 m dimension is the deck width, not a clear joist span. A 48×148 joist cannot clear-span 4.0 m (see the span table — it tops out around 2.32.7 m). The joists must rest on bearer/beam lines so the clear span between supports stays within the table; if there is no intermediate support, upsize the joists for the full span or have it designed by an engineer. The quantities below assume the joists bear on the bearer lines shown for each variant.

Number of boards: 4,000 mm (perpendicular to board direction) / (120 + 5) = 32 pcs at 6.0 m = 192 lm

Decking screws: see table below by variant

MaterialA — Ground levelB — ElevatedC — Slope
Decking boards 28×120×600032 pcs32 pcs32 pcs
Deck joists11 pcs 48×98×400011 pcs 48×148×400011 pcs 48×148×4000
Bearer beams6 pcs 48×198×60006 pcs 48×198×6000
Posts 98×9812 pcs (height per site)12 pcs (varying length)
Post bases12 pcs12 pcs
Point foundations12 pcs (approx. 590 L concrete)12 pcs (approx. 590 L concrete)
Paving slabs / blocks44–55 pcs
Gravel/aggregate2.4 m³
Weed membrane~30 m²
Decking screws~800 pcs~800 pcs~900 pcs
Diagonal bracing8–12 lm 48×9816–24 lm 48×98
Fascia boards~20 lm~20 lm~20 lm

Common mistakes

Tools you will need

Essential

  • Cross-line laser / spirit level
  • Tape measure and string line
  • Drill and driver
  • Mitre saw / circular saw
  • Post hole auger or spade
  • Countersink / pilot bit
  • Speed square
  • Sawhorses

Recommended

  • Post level
  • Concrete mixer
  • Board-spacing jigs
  • Auto-feed screwdriver (large deck)
  • Plate compactor / hand tamper

Calculate your materials

Frequently asked questions

What joist spacing should I use for decking?

For 1×6 (5/4) decking boards use 16" OC joist spacing. For thicker 2× decking you can go up to 24" OC. Always check your local building code.

Do I need a permit to build a deck?

Most jurisdictions require a permit for decks over 200 sq ft or more than 30" above grade. Check with your local building department before starting.

What wood is best for outdoor decking?

Pressure-treated pine is the most common and economical choice. Cedar and redwood are naturally rot-resistant. Composite decking is low-maintenance but costs more upfront.

Span tables in this guide are indicative. For decks at significant height, carrying heavy loads, with roof structures, or on uncertain ground, a structural engineer should verify the design. Check with your local planning authority for permit requirements and height exemptions — rules vary by jurisdiction. Timber use class (UC3/UC4, or equivalent) and preservative treatment must match the exposure conditions for your deck. Last reviewed: May 2026