How to build a stud wall
Non-load-bearing interior partition · Timber studs and plasterboard · Step by step
A stud wall is the most common way to subdivide interior space in residential construction. It is non-load-bearing and consists of a timber frame — sole plate, top plate and vertical studs — clad with plasterboard on both sides. Sound insulation is typically placed between the boards. This guide takes you through the entire process from planning through to finished skirting and architrave.
Materials you will need
Framing timber
- Sole plate (bottom plate): 48×98 mm structural timber, minimum C18 (C24 recommended) — fixed to the floor
- Top plate: 48×98 mm — fixed to ceiling or floor structure above
- Studs: 48×98 mm, measured between the fitted plates and adjusted for required clearance
- Door opening (where applicable): double studs + double header at 48×98 mm
Board cladding
- Standard plasterboard: 12.5 mm, 1,200 × 2,400 mm — for living rooms, bedrooms and hallways
- Moisture-resistant board (green/blue): 12.5 mm — for kitchens, bathrooms and utility rooms
- Fire-rated board (red): where a fire compartment wall is required (REI 30/60)
Insulation
- Acoustic insulation: 70 mm mineral wool (stone wool or glass wool) — reduces airborne sound transmission by approximately 5–8 dB
- Thermal insulation is rarely necessary for an interior stud wall
- In wet rooms: use moisture-resistant insulation (stone wool)
Fixings
- Plates to concrete (powder-actuated): Hilti/Spit shot fasteners — fast installation into solid concrete, requires specialist tool
- Plates to concrete (expansion anchors): Ø8 mm, minimum 50 mm embedment, max 600 mm centres — use where powder-actuated fasteners are not suitable
- Plates to timber: 4.5×90 mm structural screws, 600 mm centres
- Studs to plates: 4.5×75 mm angle brackets or toenailed with 3.1×90 mm nails
- Plasterboard: 3.5×35 mm drywall screws, 200 mm centres at edges, 300 mm centres at intermediate studs
- Vapour barrier: 0.15 mm polyethylene film (only at external walls or where required) + vapour-barrier tape at joints
Trim and architrave
- Skirting board: 12×58 mm or 15×70 mm — along the wall/floor junction
- Cornice/coving: 12×58 mm — along the wall/ceiling junction (optional)
- Door architrave: 21×70 mm — framing the door opening
- Adhesive and pin nailer (23 ga nails, 35–50 mm) for trim
Drawings
Step by step
Step 1 — Planning and setting out
Mark the wall position on the floor with a chalk line or laser level. Mark where any door openings will be. Remember that the finished wall will consume approximately 125 mm of floor area (two plasterboard sheets + stud + plates).
- Check that the planned position does not conflict with pipes, cables or structural elements in the ceiling
- Plumb up from the floor line to the ceiling using a laser or plumb bob
- Mark stud positions on the plates (600 mm centres) before fixing
Step 2 — Fix the sole plate
Lay the sole plate along the chalk line. At door openings, the sole plate is cut and stops at the inner face of the door studs — the sole plate must not run across a door opening.
- Concrete floor: use Ø8 mm expansion anchors, minimum 50 mm embedment depth, at 600 mm centres
- Timber floor: 4.5×90 mm screws through the plate and floor boards and into the joist
- Always fix at stud positions — avoid fixing mid-bay between studs
Step 3 — Fix the top plate
Plumb up from the sole plate and fix the top plate to the ceiling. Into concrete: expansion anchors. Into timber floor structure: screw into the joist — never fix only into floor boarding.
Step 4 — Studs
Studs are set at 600 mm centres, measured from centreline to centreline. This gives optimal use of 1,200 mm wide plasterboard sheets — two sheets always meet on a stud.
- Measure stud length directly between the fitted plates and subtract the required clearance — do not calculate from room height
- Start with corner studs, then work inward from the corners
- Fix with stud angle brackets or toenailing — minimum 2 nails or screws per side
- Check with a spirit level: each stud must be perfectly plumb
Step 5 — Door framing
At door openings, double studs are set on each side of the opening. A double header of the same section (48×98 mm) is fitted above the opening to distribute the plasterboard load across the gap.
- Standard rough opening width: 860 mm for a 900 mm door (including frame), or 760 mm for an 800 mm door
- Double studs are bolted together with 4.5×90 mm screws at 400 mm centres
- Short cripple studs run from the header up to the top plate at 600 mm centres
Step 6 — Services: pipes, cables and ventilation
Before closing the wall: install all pipes, cables and ventilation ducts. This is the last opportunity to do so without opening up plasterboard.
- Route cables through studs via pre-drilled Ø20–25 mm holes (do not notch more than approximately one-third of the stud width)
- Mark electrical back-box positions on the studs in pencil
- Confirm with a qualified electrician that wiring complies with the relevant electrical regulations
Step 7 — Insulation
Cut mineral wool to the correct width (600 mm, matching the stud spacing) and press firmly between the studs. The insulation must sit tightly with no air gaps.
- Cut with a knife against a straight edge — add approximately 10 mm to the width for a friction fit
- Fill carefully around electrical back-boxes — voids reduce sound reduction performance
- Typical sound reduction with 70 mm mineral wool: Rw ≈ 43–48 dB (depending on plasterboard thickness)
Step 8 — Vapour barrier (where required)
A vapour barrier is required at external walls and in wet rooms — not in interior stud walls between heated spaces. Installing a vapour barrier in a purely internal partition is unnecessary and can trap moisture.
- The vapour barrier goes on the warm side (room side) of the insulation in an external wall
- Overlap joints by at least 200 mm and seal with vapour-barrier tape
- Staple to the studs
Step 9 — Plasterboard, first side
Start on the side with the best access. Lift the board up to the ceiling — use a board lifter or wedges — and fix from the centre outwards towards the edges.
- Screw spacing: 200 mm at edges, 300 mm at intermediate studs
- Screws should be set approximately 12 mm from the board edge — too close to the edge will cause the plaster core to break
- The screw head should sit 0.5–1 mm below the face (a slight dimple) without tearing through the paper
- Always start with a full board in the corner — fill with cut pieces towards the opposite wall
- Stagger horizontal joints on opposite faces of the wall to improve sound reduction
Step 10 — Jointing and sanding
All joints and screw heads are filled and sanded to a smooth surface in three coats:
- Tape coat: bed paper joint tape into all butt joints and apply a thin coat of joint compound
- Second coat: after drying (approximately 24 h), apply a wider, thinner coat
- Finish coat + sanding: rake lighting reveals any ridges — sand with 120-grit paper
Step 11 — Plasterboard, second side
Fix plasterboard on the second side. Ensure that vertical joints do not align with those on the first side — offset joints improve sound reduction performance.
Step 12 — Trim and finishing
- Prime and paint the wall before fitting trim — saves masking tape
- Cut skirting and architrave at 45° mitre joints using a mitre saw
- Fix with adhesive (construction adhesive) + pin nailer, 35 mm nails
- Fill the gap between trim and wall/floor with paintable acrylic sealant
Rules of thumb and dimensions
| Parameter | Value |
|---|---|
| Stud spacing (centres) | 600 mm (standard), 400 mm for heavier cladding |
| Stud section | 48×98 mm (standard), 48×148 mm for enhanced acoustic performance |
| Plasterboard thickness | 12.5 mm standard, 15.0 mm for fire compartment walls |
| Insulation thickness | 70 mm (matching stud width) |
| Total wall thickness | approx. 125 mm (48×98 mm stud + 2× 12.5 mm) |
| Screw spacing, edges | 200 mm |
| Screw spacing, field | 300 mm |
| Screw length, plasterboard | 35 mm (single layer), 55 mm (double layer) |
| Door rough opening width | 860 mm for 900 mm door, 760 mm for 800 mm door |
Common Mistakes
- ✗Forgetting the top plate in the material count — you need as much top-plate timber as bottom plate; count both in your estimate
- ✗Wrong stud length — studs fill the gap between bottom and top plate, not floor to ceiling; stud length = room height minus two plate thicknesses
- ✗Openings without doubled studs and a lintel — door openings require a trimmer stud each side, king studs and a lintel above to carry the load
- ✗Insufficient waste allowance — cuts at corners, openings and joints typically add 10–15% waste to stud and board quantities
- ✗Confusing nominal and actual dimensions — a "48×98 mm" stud actually measures slightly less; always use actual sizes for detailed design
- ✗Forgetting noggings — horizontal blocking halfway up the studs increases racking strength and is required by most plasterboard fixing guides
Calculate your materials
Use our calculators to find the exact quantities and cost for each material:
Frequently asked questions
What is standard stud spacing?
Standard stud spacing is 16" OC for load-bearing and most partition walls. 24" OC is allowed for non-load-bearing partitions and can save material.
What stud size should I use?
For partition walls use 2×4 studs. For exterior walls or where extra insulation depth is needed use 2×6 studs.
Do I need a vapor barrier in a partition wall?
Vapor barriers are required in exterior walls and walls against unconditioned spaces. Interior partition walls between conditioned rooms typically do not need one.
References
- → Gyproc White Book — complete stud wall and partition installation guide
- → Rockwool Technical Handbook — mineral wool insulation installation
- → Knauf Technical Guide — drywall and partition installation details
- → Local building authority — technical requirements for fire compartmentation, acoustic separation and wet room construction