Skip to content
Concrete

Concrete Bag Calculator — How Many Bags Do I Need?

Calculate how many bags of concrete mix you need for a slab, footing or post holes. Supports 25 kg and 40 kg bags in metric and 60 lb and 80 lb bags in imperial, with waste factor and a ready-mix comparison.

1Dimensions (m)

Slab thickness — e.g. 0.10 = 10 cm

2Concrete and price
Presets

Presets are typical European merchant prices — an estimate to start from, not a quote from your supplier. Type over any of them.

3Additional materials

Preview

? length??
Enter dimensions to see the calculation

Save to project

Free to try — no sign-up

Draw it once. Every surface prices itself.

Measure the room on screen and its floor, wall and ceiling areas fill the calculators in for you — insulation, boards, paint, tiles — each with its own quantity and cost against one running total.

Free covers one project, three saved calculations and a two-room plan. What a Project Pass adds →

How the bag count is calculated

  • 1Volume = length × width × depth (m³ or ft³)
  • 2Add 5–10% for waste, uneven formwork and spillage
  • 3Bags needed: volume ÷ yield per bag (0.012 m³ for a 25 kg bag, 0.019 m³ for 40 kg; 0.45 cu ft for a 60 lb bag, 0.6 cu ft for an 80 lb bag)
  • 4Ready-mix alternative: order in m³ or cubic yards, rounded up to the nearest 0.25 m³
  • 5Mix strength: C20/25 for most domestic slabs, C25/30 for driveways, C30/37 for structural footings
  • 6Round bags up to whole bags — partial bags can't be poured later

Worked example

Concrete slab: 4 × 3 m at 0.1 m deep — 13 × 10 ft at 4 in — = 1.2 m³. With 8% waste: 1.3 m³, or 1.7 cubic yards.

You need 109 bags of 25 kg premix — or 77 bags of 80 lb — and approximately 5–6 bags of 40 kg premix per m² at 100 mm depth. For ready-mix, order 1.5 m³, which is 2 cubic yards.

Frequently asked questions

How many bags of concrete for a 10×10 slab?

A 10×10 ft slab at 4 inches deep = 0.93 m³. With 8% waste: ~1 m³. That is approximately 83 bags of 25 kg premix or 53 bags of 40 kg premix (each 40 kg bag yields approx. 0.019 m³).

How much concrete does one bag make?

A 25 kg bag yields approximately 0.012 m³; a 40 kg bag approximately 0.019 m³. In US sizes, a 60 lb bag makes about 0.45 cu ft and an 80 lb bag 0.6 cu ft. Check the bag — yields vary slightly between products.

When is ready-mix cheaper than bags?

Ready-mix is usually more economical above approximately 1 m³ — around 1.3 cubic yards — and gives more consistent quality. Below that, bagged premix is more practical. Check truck access before ordering ready-mix.

How long does bagged concrete take to cure?

Concrete reaches approximately 70% of its design strength after 7 days and 99% after 28 days. Keep it moist for at least 7 days and don't load it during that time.

Plan the whole job

One calculation is one line of a job. With the floor planner you draw the room once and every calculator on the site fills itself from those measurements, with the openings taken off. The project manager then holds every room and trade against one budget, and tracks what things actually cost as the invoices arrive.