Pricing a job

How to price a renovation job

The same arithmetic whether the house is yours or the client's. One commits your savings and the other commits your reputation, but the quantities do not care which.

Materials, hours and overheads in one total — free to start. How the project planner works →

The formula

materials + labour + overheads + margin

If you are pricing your own house, drop the last term and keep the other three. That is the only difference between a budget and a quote, and it is worth being clear about, because the mistakes in both are identical.

Materials: a third of the money, and all of the precision

Materials are roughly 30–40% of a renovation. That is the smaller half, and it is also the only half you can get exactly right, because it is arithmetic rather than judgement. Getting it exactly right is worth doing precisely because everything else on the page is an estimate.

Labour: the other two thirds

Labour is typically 60–70% of the total. It varies by job — around 67% on a kitchen, 69% on a bathroom, higher again on an extension — but the shape is always the same: the work costs more than the stuff.

Estimate it in hours per task, not days per room. Days per room is where the optimism gets in. Hours per task forces you to name the task, and naming the task is what surfaces the second fix, the making good, and the day lost waiting for a delivery.

Overheads: the lines that belong to no room

Skip hire, scaffolding, building control, delivery charges, parking, welfare, tool hire, insurance. They belong to the job rather than to any one room, which is exactly why they get missed — a budget organised by room has nowhere to put them. Give them their own block and total it separately.

Contingency is not margin

Contingency — 10% on cosmetic work, 15–20% once walls come open — is for what the job turns out to need. Margin is what the business earns for doing it. Mix them and you will finish a job on budget and still have made nothing, because the rot behind the bath was quietly paid for out of your wages.

The four places it goes wrong

  1. 1Quantities taken from floor area instead of a real take-off, so everything downstream inherits a rounding error.
  2. 2Waste applied as one number across materials that waste at different rates.
  3. 3Overheads left out because they belong to no room.
  4. 4Labour estimated once in week one and never revisited while the scope moved.

Doing it here

Draw the rooms once and the measurements price the materials — the right quantity, with the waste factor for the pattern actually chosen, in the units the merchant sells. Add hours per task and the overheads that belong to the job, and the whole thing totals in one place that you can hold against what the work really cost.

What each trade actually needs

Pricing a trade means knowing its build-up. These cover what goes into each one, and the waste that comes with it.

Common questions

How do you price a renovation job?

Materials plus labour plus overheads, then margin if you are quoting for someone else. Work the materials out from measured quantities rather than from a rate per square metre, estimate labour in hours per task, and list overheads — skip hire, scaffolding, building control, delivery — as their own lines rather than burying them in a rate.

What percentage of a renovation is labour?

Typically 60% to 70% of the total, with materials making up the other 30% to 40%. It varies by job: kitchens run around 67% labour, bathrooms around 69%, and extensions higher still at roughly 71%. Any estimate that treats materials as the main cost is already wrong by a wide margin.

How much should a contractor mark up materials?

Commonly 15% to 25%. That is not profit on the goods — it covers the time spent specifying, ordering, collecting, chasing and returning them, plus the risk of a price change between quote and purchase. Margin on the job as a whole is a separate line.

What is the difference between contingency and profit?

Contingency is money set aside for what the job turns out to need — rot, old wiring, a floor that is not level. Profit is what the business earns for doing the work. Treating one as the other is how a job finishes on budget and still loses money.

Why do renovation estimates come in low?

Four reasons, usually together: quantities taken from floor area rather than from a real take-off, waste under-counted because it varies by pattern rather than by material, overheads left out because they belong to no single room, and labour estimated once at the start and never revisited as the scope moves.

Percentages here are typical industry ranges for planning, not rules. Labour share, markup and waste all move with the trade, the region, the condition of the building and who is doing the work. Price your own jobs from your own rates and your own merchant's quotes.