Step by step
How to keep a renovation on schedule
Renovations rarely run late because somebody worked slowly. They run late because something was done before the thing it was waiting on, or because the only copy of the running order was in one person’s head. A renovation is an order of operations, and a to-do list cannot hold one. A board can, a calendar holds the dates that will not move, and between them you stop having to remember.
Free to use, and it works on a phone — which is where a board gets used. Tracking what it costs →
What order does this go in?
Tick the work a room needs, in whatever order it occurs to you. You will get it back in the order it is done, with the reason each step sits where it does — and the gap between those two lists is the reason a board beats a list.
What this room needs
Tick them in any order you like — the list below is the order they happen in.
6 steps, in order
- 1
Strip out
Everything after this is quicker in an empty room, and you cannot price what you have not uncovered.
- 2
First fix — plumbing
Pipework runs inside the structure, so it goes in while the structure is still open.
- 3
Plasterboard
The first thing that closes the wall. Check every service is in and tested before it does.
- 4
Plastering or jointing
Wet, and it has to dry. Everything after it is waiting on that rather than on a trade.
- 5
Tiling
Onto a dry, flat, finished background — which is what the three steps above exist to produce.
- 6
Flooring
Late, so the floor is not a work surface for the rest of the job.
That is not the order you ticked them in. On a board those become columns — what is waiting, what is booked, what is being done — and the order stops living in somebody's head.
This is the common sequence for a domestic refurbishment, not a regulation. Trades overlap and jobs get re-sequenced around a delivery or whoever is available. What does not move is the handful of real dependencies named above — services before the boards that cover them, wet trades before what has to stay dry, the floor before the trim that sits on it.
The whole way through
- 1
Write the work down against the room it happens in
Tasks belong to rooms, because that is how a renovation is actually organised — and it is how they add up to something you can read later.
- ·Each room carries its own checklist, and each task can take an estimate in hours and a date it is due.
- ·Hours typed here are the ones that reach the budget as your own labour, so a schedule and a cost are the same act of writing it down.
- ·A room also has a status of its own — not started, in progress, done — which is what the rest of the screens colour themselves from.
- 2
Open the Board and see the whole job at once
The Board tab collects every task in the project, across every room, into four columns: waiting, scheduled, being done, done.
- ·A checklist has two states and no sense of order, so "the tiles are ordered but not laid" had nowhere to live. A column is where it lives.
- ·Cards carry the room they came from, so the board stays readable once there are four rooms on it rather than one.
- ·The columns run left to right in the order the work moves through them, which means the board is also a picture of how far along you are.
- 3
Move a card with the arrows, not the mouse
Every card has arrows that move it one column. That is the real mechanism — dragging is the convenience on top.
- ·Drag and drop does not fire on a touchscreen at all, and this gets used on a phone standing in the room. The arrows work everywhere.
- ·They are reachable by keyboard and announced to a screen reader, which a drag is not.
- ·Moving a card to Done ticks the task, and unticking something in Done sends it back to being done rather than all the way to the bottom of the list — because that is what unticking it means.
- 4
Put the fixed dates on the Schedule
Some things are not tasks, they are appointments: a contractor arriving, a delivery, an inspection, a meeting.
- ·Each takes a date, optionally a time, who it is with, and a note — and can be tied to the room it concerns.
- ·They are typed so they read at a glance: a delivery and an inspection do not look the same on the month.
- ·These are the things everything else moves around, which is why they are kept apart from the work itself.
- 5
Give the rooms dates and read the timeline
With a start and an end on a room, it becomes a bar — and several rooms become the shape of the job.
- ·Bars take their colour from the room’s status, so what is finished and what has not started read without a legend.
- ·A room with no dates of its own falls back to the project’s start and deadline. If neither has dates, the room does not appear — that is the timeline being empty rather than wrong.
- ·This is the view that answers "will the kitchen be usable at Christmas", which no checklist can.
- 6
Keep the order honest, not optimistic
Most renovation overruns are a sequence problem rather than a speed problem: something was done before the thing it was waiting on.
- ·The real dependencies are few — services before the boards that cover them, wet trades before what has to stay dry, the floor before the trim that sits on it.
- ·Everything else is convention and can be re-sequenced around a delivery or whoever is available that week.
- ·Put the dependent things in the backlog rather than in Scheduled. A date on something that cannot start yet is the thing that makes a plan collapse.
- 7
Check it where you can act on it
The board and the schedule are for during the work, not for the planning weekend. Use them on a phone, in the room, with the dust.
- ·Everything works at phone width, which is why the arrows exist and why the columns scroll rather than shrink.
- ·A card moved on site is a record you still have on Monday, which the conversation you had with the plumber is not.
- ·Nothing here notifies anybody. It does not chase you, send email or feed a calendar app — it holds the plan, and you look at it.
Where each thing belongs
| If it is… | It goes | Because |
|---|---|---|
| Work that can move | On the Board | It has a stage, and the stage is the useful fact about it |
| A date you do not control | On the Schedule | Everything else is sequenced around it |
| A span of days | On the Timeline | Give the room a start and an end and it becomes a bar |
| The state of a whole room | Room status | It colours the timeline and the room list |
| Hours you expect it to take | On the task | The same number reaches the budget as your own labour |
The four columns are the same four everywhere: waiting, scheduled, being done, done. A task is in exactly one of them, and the one it is in is the answer to "what is happening with that".
What this is not
- ·Not a reminder service. Nothing notifies you, emails you or feeds a calendar app — it holds the plan and shows it when you open it.
- ·Not shared working. A share link is read-only; nobody else can move a card, and two people cannot run one board between them.
- ·Not critical-path planning. It does not compute what a delay does to everything downstream, or tell you which task is the one holding up the job.
- ·Not a rule about sequence. The order above is the common one for a domestic refurbishment; the real dependencies are named, and the rest is convention.
The work you are sequencing
The board holds the order. These explain what each step involves.
Common questions
What is the difference between a task and an appointment?
A task is work that has to happen and can move: boarding the walls, second fix, laying the floor. An appointment is a fixed point you do not control — the electrician arrives on Tuesday, the worktop is delivered on the 14th, the inspection is booked. Tasks live on the Board and move between columns; appointments live on the Schedule and sit still. Keeping them apart is what makes the board usable, because a board full of immovable dates is just a calendar with extra steps.
Why are there arrows on the cards as well as dragging?
Because dragging does not work on a phone. HTML5 drag and drop does not fire on a touchscreen, and this gets used standing in the room being renovated. So the arrows are the real mechanism — they work on any device, they can be reached with a keyboard, and a screen reader announces them. The drag is the nicety for people at a desk.
If I tick a task off in the room, does the board know?
Yes, and the other way round. They are the same fact, not two records of it: ticking a task puts its card in Done, and moving a card to Done ticks it. They cannot drift apart, because if they could you would have a task that looked finished on the board and unfinished in the room, and every progress figure drawn from it would be wrong.
What happens if I untick something that was finished?
It goes back to being done rather than back to the start. Unticking something in the Done column means "this is not finished after all", and the honest reading of that is that it is being worked on again — not that it has fallen all the way back to a backlog it left days ago.
My timeline is empty. Why?
A room becomes a bar only when it has a start and an end. If the room has no dates it falls back to the project’s start date and deadline, and if the project has none either there is nothing to draw. Give the project a start and a deadline and every room appears at once; then give individual rooms their own dates where they differ.
Will it remind me about anything?
No. There are no notifications, no emails and no calendar feed to subscribe to. It holds the plan and shows it to you when you open it. That is a deliberate limit rather than a missing feature — anything that pushed at you would need your email and your permission, and this works without either.
Can I share the schedule with a builder?
You can share the whole project, which carries the rooms and their costs, as a read-only link. There is no separate schedule-only link, and the person opening it cannot tick anything off — it is something to read, not somewhere to work together.
Does this need a paid plan?
No. The board, the schedule, the timeline and room status all work on the free plan, on your own device, with one project. Paid plans are about keeping more — more projects, more saved calculations, photos and cloud sync so the same board opens on your phone and your laptop.
Free to try — no sign-up, nothing to install. The whole job, in seven steps →
Free to try — no sign-up
Draw it once. Every trade prices itself.
Measure the room on screen and its floor, wall and ceiling areas fill the calculators in for you — insulation, boards, paint, tiles — each with its own quantity and cost against one running total.
Free covers one project, three saved calculations and a two-room plan. What a Project Pass adds →